Timeline

Dates are as recorded in the cited documents. “Forecast” means SDEN or the Council expects it, not that it has happened.

Promised v actual dates

MilestonePromisedActual / forecastGapSources
Phase 1: 800 homesby 2022 (2017 model)July 2023 build-outabout 12 monthsS11, S3
Lavenders: contracts signedbefore end Mar 2019not signed as of Mar 20267+ years and continuingS9, S3
Lavenders: planning applicationQ1 2025not submitted as of Mar 202612+ months and continuingS7, S3
Lavenders: heat supply2025 (DESNZ), end 2025 (brochure), mid 2026 (2025–28 plan)forecast from mid 202712–18+ months and continuingS19, S12, S7, S3
ERF heat connectionoriginal date not foundforecast 1 Apr 2027n/aS3, S6

Key dates

  1. SDEN incorporated (Companies House 10022446). Verified

    Sources: S1

  2. First heat supplied to New Mill Quarter from back-up gas boilers. Verified

    Sources: S3, S7

  3. Shareholdings Board paper: extend the network about 700 m to Lavenders; Clarion needed contracts signed before end of March 2019. Verified

    Sources: S9

  4. Beddington energy recovery facility (ERF) operational. Verified

    Sources: S3, S6

  5. Off-site low-carbon (landfill gas) heat effective for the network. Verified

    Sources: S3, S7

  6. CIPFA review (commissioned by the Council) published to Strategy & Resources Committee; says earlier model assumptions were not prudent. Verified

    Sources: S11

  7. Full build-out of heat interface units at New Mill Quarter (company plan). Likely

    Sources: S3

  8. Government pipeline lists Lavenders extension: ‘initial heat’ 2025, cost ‘circa £2M’. Verified

    Sources: S19

  9. SDEN brochure says 348 further homes ‘forecasted to complete before the end of 2025’. Verified

    Sources: S12

  10. One outage of about 4h15m reported by SDEN (1:30–5:45am). Verified

    Sources: S3

  11. Ofgem regulation of heat networks goes live; existing operators must register by 26 Jan 2027. Verified

    Sources: S22

  12. Council business plan 2026–29: Lavenders planning application still to be submitted; connection ‘from mid 2027’. Verified

    Sources: S3, S4

  13. ForecastHeat from the ERF (up to 15 MW) forecast to start. Verified

    Sources: S3

  14. ForecastLavenders connection forecast. Verified

    Sources: S3

Date check pending: the date of the 2019 First-tier Tribunal decision on release of the 2017 model review is being checked against the BAILII record before it is added. Unverified